Question 1

Under 21 CFR 211.180(c), when may electronic CGMP records kept at another site satisfy inspection availability requirements?

  1. A

    When FDA pre-approves the remote server in writing for each batch

  2. B

    When records are immediately retrievable by computer or electronic means

  3. C

    When printed originals at the site replace electronic retrieval paths

  4. D

    When OTC dating exemptions under §211.137 waive electronic retrieval

Show official answer

Accepted answer: B

Explanation

B is correct. Section 211.180(c) treats records immediately retrievable electronically as meeting on-site availability requirements. Option A invents a per-batch FDA server approval step not stated in the rule.

Question 2

A U.S. site revises its tablet coating SOP. Under 21 CFR 211.100(a), which approval path applies to the written production procedures?

  1. A

    Drafted by manufacturing alone without quality control unit review

  2. B

    Drafted, reviewed, and approved by appropriate units and the QC unit

  3. C

    Approved by marketing after launch without manufacturing or QC sign-off

  4. D

    Posted as draft text on a public website awaiting informal comments

Show official answer

Accepted answer: B

Explanation

B is correct. Section 211.100(a) requires production procedures, including changes, to be drafted, reviewed, and approved by appropriate organizational units and the QC unit. Option A omits the explicit QC review step in the regulation.

Question 3

When setting up a global regulatory documentation tracker, which ICH M4(R4) consideration supports lifecycle planning for excipient sections?

  1. A

    Avoiding lifecycle updates after the first marketing authorization

  2. B

    Considering future lifecycle potential when choosing document granularity

  3. C

    Eliminating Module 2 quality overall summaries from the global tracker

  4. D

    Using national paper formats exclusively in each region without planning

Show official answer

Accepted answer: B

Explanation

B is correct. ICH M4(R4) lists future lifecycle potential among granularity considerations for global documentation. Option A contradicts ongoing lifecycle management expectations in M4 planning.

Question 4

During an internal SOP harmonization workshop across EU and U.S. sites, which RAPS fairness expectation applies?

  1. A

    Apply U.S. CGMP and ignore applicable EU differences

  2. B

    Apply EU rules at U.S. manufacturing sites without local law

  3. C

    Hide regional requirements from operations staff during harmonization

  4. D

    Apply the appropriate regulatory standards to each case and site

Show official answer

Accepted answer: D

Full explanations are in practice mode. Start the free test →

Question 5

According to the RAPS Code of Ethics, how should regulatory professionals treat information in project communications?

  1. A

    Share leadership summaries that omit known compliance gaps from reports

  2. B

    Present information in project communications accurately and completely

  3. C

    Defer final wording of safety data to the marketing department

  4. D

    Limit formal documentation to verbal updates during stand-up meetings

Show official answer

Accepted answer: B

Full explanations are in practice mode. Start the free test →

Question 6

Under 21 CFR 314.110(b)(1)(i), what review cycle does a Class 1 NDA resubmission start?

  1. A

    A new two-month review cycle beginning when FDA receives the resubmission

  2. B

    A new six-month review cycle beginning when FDA receives the resubmission

  3. C

    A one-hundred-eighty-day initial review cycle identical to the original NDA

  4. D

    A sixty-day EU type II variation assessment under Regulation 1234/2008

Show official answer

Accepted answer: A

Full explanations are in practice mode. Start the free test →

Question 7

Under Regulation 1234/2008 Article 8(1), what default deadline applies to a type IA notification after implementation for a decentralised marketing authorisation?

  1. A

    Before implementing the change, within seven days of the change

  2. B

    Within forty-five days of an unforeseen variation classification recommendation

  3. C

    Within sixty days after acknowledgement of a valid type II application

  4. D

    Within twelve months following implementation of the type IA variation

Show official answer

Accepted answer: D

Full explanations are in practice mode. Start the free test →

Question 8

FDA receives a Class 1 efficacy supplement resubmission on 3 March. Under 21 CFR 314.110(b)(1)(i), when does the new review cycle begin assuming proper classification?

  1. A

    3 January, two months before FDA receives the Class 1 resubmission

  2. B

    3 May, two months after FDA receives the Class 1 resubmission

  3. C

    3 September, six months after FDA receives the Class 1 resubmission

  4. D

    3 March, on the date FDA receives the Class 1 resubmission

Show official answer

Accepted answer: D

Full explanations are in practice mode. Start the free test →

Question 9

A CRO refuses to share stability raw data needed for an EU/U.S. filing. Which response best aligns with the RAPS honesty duty and 21 CFR 211.194 laboratory records?

  1. A

    File the certified summaries and audit the CRO raw data after approval

  2. B

    Accept the trend graphs now and leave the chromatograms stored at the CRO

  3. C

    Require complete stability records, including the underlying raw data

  4. D

    Use the vendor summary now and retrieve raw data at the next annual update

Show official answer

Accepted answer: C

Full explanations are in practice mode. Start the free test →